PROVINCIAL ASSEMBLY OF SINDH
PUBLIC HEALTH ENGINEERING AND RURAL DEVELOPMENT DEPARTMENT
LIST OF STARRED ASSEMBLY QUESTIONS AND ANSWERS FOR
MONDAY, THE 7TH SEPTEMBER, 2026
219 *Mr. Muhammad Daniyal:
Will the Minister for Public Health Engineering be pleased to State:-
Location-wise number of R.O plants installed in the District East Karachi during 2018-2023 along with amount incurred?
ANSWER
MR. MUHAMMAD SALEEM BALOCH, SPECIAL ASSISTANT FOR PUBLIC HEALTH ENGINEERING:-
It is intimated that the installation of R.O Plants/ Filtration Plants in District East, Karachi is not under the mandate of Public Health Engineering and Rural Development Department. Hence, no any R. O. Plant installed in the District East, Karachi during 2018-23 in District East, Karachi.
1720 *Mr. Muhammad Daniyal:
Will the Minister for Public Health Engineering be pleased to State: -
Number of water supply schemes are operational in Larkana Division as on 01-01-2025?
ANSWER
MR. MUHAMMAD SALEEM BALOCH, SPECIAL ASSISTANT FOR PUBLIC HEALTH ENGINEERING: -
The Larkana Division comprises of five (05)Revenue Districts, namely Larkana, Kamber-Shahdadkot, Jacobabad, Kashmore-Kandhkotand Shikarpur. At present, five (05) Public Health Engineering (O&M) Divisions are functioning in the Division, which are providing drinking water facilities in rural areas.
It is further stated that a total of 124 rural water supply schemes are operational. The details of urban water supply schemes pertaining to Local Councils may be obtained from the concerned agencies through the Local Government Department.
The district-wise breakup of rural water supply schemes maintained by the PHE Department is at Annexure placed on the Table of the House.
2179 *Syed Muhammad Usman:
Will the Minister for Public Health Engineering be pleased to State: -
Number of ongoing and completed pure drinking water schemes initiated between May 2024 and 2025 in the province?
ANSWER
MR. MUHAMMAD SALEEM BALOCH, SPECIAL ASSISTANT FOR PUBLIC HEALTH ENGINEERING: -
It is intimated that the year wise detail of ongoing and completed Schemes of Pure Drinking Water Supply during the Financial Year 2023-24 and 2024-25, in the province are as under:
|
Financial Year |
Number of Schemes |
Completed Schemes |
||
|
Ongoing |
New |
Total |
||
|
2023-24 |
79 |
44 |
123 |
18 |
|
2024-25 |
103 |
0 |
103 |
32 |
|
Total:- |
182 |
44 |
226 |
50 |
2180 *Syed Muhammad Usman:
Will the Minister for Public Health Engineering be pleased to State: -
(a) Is it a fact that people were recruited inP.H.E Department during 2023-24 and 25;
(b) If answer to (a) above is affirmative, Grade-wise detail thereofalongwithprocedure followed for the same?
ANSWER
MR. MUHAMMAD SALEEM BALOCH, SPECIAL ASSISTANT FOR PUBLIC HEALTH ENGINEERING: -
It is intimated that total 358 persons were appointed in the PHE & RD Department during the years 2023, 2024 and 2025. The Grade- wise details are as under: -
|
S: No. |
Designation along with Grade |
Total persons appointed |
Mode of appointment |
|
1. |
Assistant Engineer (BS-17) |
63 |
Through SPSC. |
|
2. |
Sub-Engineer (BS-11) |
275 |
Through IBA Sukkur on contract basis |
|
3. |
Pump Operator (BS-04) |
02 |
Regular under 5% Differently abled persons quota |
|
4. |
Naib Qasid (BS-01) |
03 |
Regular under 5% Differently abled persons quota |
|
5. |
Beldar (BS-01) |
08 |
Regular under 5% Differentlyabled persons quota |
|
6. |
Chowkidar (BS-01) |
07 |
Regular under 5% Differentlyabled persons quota |
|
Total: |
358 |
|
|
KARACHI: G.M UMAR FAROOQ
DATED THE 6TH SEPTEMBER, 2026 SECRETARY
PROVINCIAL ASSEMBLY OF SINDH